The next block of racks is due to go live in three weeks. Then the transformer's annual oil report arrives: two dissolved gases are higher than last year, and a third has crossed the laboratory's reporting limit.
The electrical contractor needs to know what this means for the load change. Another sample may help, but what should it answer, and when does the team need the result?
First, the owner's transformer engineer must assess the actual gases, levels, alarms and operating history. A repeat sample must never delay an action already required by protection, the manufacturer or the site's operating procedure. There is no universal wait-for-confirmation rule.
Once that urgent assessment is made, the investigation has a more useful question: is the gas still climbing, and how fast? A repeat sample can help only if it can fairly be compared with the earlier one and reported in time for the decision. The owner, with its transformer engineer or manufacturer, decides how to operate the equipment.
Why the date matters as much as the number
Heat and electrical stress can break down transformer oil and its paper insulation, producing gases that dissolve in the oil. Measuring them is dissolved gas analysis, or DGA. Gas type and amount help describe a problem, but the rate and change over time matter too, as ASTM D3612's public significance statement explains.
The US Bureau of Reclamation's transformer maintenance manual asks for every analysis to be compared with earlier results. It gives particular weight to a sudden rise and the rate of production, while treating acetylene as significant even in small amounts. The manual is from 2000; its numerical interpretation tables are not a substitute for the guide your engineer uses now.
A rate needs two things: results you can trust to be comparable, and the real time between them. Your two results are a year apart, so the rate they give is only an average over that year. It cannot tell you whether the gas crept up steadily or sat still for eleven months and then started to climb.
The figure uses assumed numbers, not limits or typical values. One gas measured 20 ppm last year and 50 ppm this year. (Parts per million by volume and microlitres per litre are the same quantity.) For this example only, the bars are assumed expanded uncertainties of ±15%, with coverage factor k = 2. They are not a laboratory's statement or an alarm rule. Both histories fit the annual results. Three weeks later, the steady history adds less than 2 ppm; the late rise, if it continues at 1 ppm a day, adds 21 ppm. The difference shows why the timing of the next sample matters, not whether a transformer is safe.
Could the sample explain the change?
Reclamation's manual says that when hydrogen, moisture or gases from the air jump from one analysis to the next, sampling or handling can be the explanation. It recommends checking a suspect analysis with another sample. That check accompanies, rather than postpones, any operating response required by the actual result or event. Our earlier guide to choosing between action, verification, trend monitoring and a repeat sample puts that priority first.
For dissolved gas, three things can move a result without anything changing inside the transformer.
- The valve. Oil trapped in the drain valve and connecting pipe does not circulate. Reclamation describes hydrogen collecting there when the sun heats the tank, or forming through galvanic action where galvanised or black iron pipe meets a brass valve. Use the same valve and flush it the same way. Avoid the small side ports on large drain valves: the manual says they cannot flush the valve properly.
- Air. Reclamation recommends glass syringes so bubbles can be seen and expelled; a small air leak into a metal vacuum bottle can go unnoticed. In CIGRE tests reported in 2007, a bubble larger than about 1% of the sample volume lowered measured hydrogen by about 35%. Expel air while filling, then seal the syringe.
- Light and heat. Those tests found that sunlight raised hydrogen in aged oil in a stored syringe. Eight days at 60 °C in the dark, without air, changed little for the tested oil; about 20 days at 90 °C produced extra hydrogen. This heat-related effect in some mineral oils is called stray gassing. The authors recommend room-temperature, dark storage. Reclamation asks for the syringe to go straight back into its shipping container. Agree a route with the laboratory that avoids sunlight and strong heat.
For the sampling procedure, use clause 4.2 of IEC 60475:2022. It covers mineral oils, synthetic and natural esters, and silicones. IEC 60567:2023, the gas-analysis guide, now points there for taking oil from equipment. Both are listed on VeriFluid's transformer oils page and in its method library.
The transformer's state at sampling matters too. Reclamation cautions that dissolved gas results are unreliable if the transformer has been switched off and allowed to cool, if it is new or if it has had less than one to two weeks of continuous service after oil processing. The manual also stresses keeping a history of overloads, cooling problems, nearby lightning and through-faults (faults elsewhere on the network that drive heavy current through the transformer), because that history helps explain what a change in the gases means.
Taking oil from an energised transformer is electrical work. It belongs to people your site has authorised for that equipment, working under its permit and safety rules. Reclamation, for example, says not to sample while there is negative pressure at the valve, because air drawn into an energised transformer could be disastrous. A laboratory can specify the container and the record; the work at the valve is the site's responsibility.
A year between samples can hide a late rise
Once both results can be trusted, the arithmetic is simple: divide the change by the time between the samples. Reclamation counts only the days the transformer was on load and leaves out any days it was out of service.
With the assumed numbers above, 30 ppm over 365 days is about 0.08 ppm a day. The same 30 ppm over three weeks would be about 1.4 ppm a day, more than seventeen times faster. That is why each result needs the date its sample was taken beside it, not just the date of the report.
Each result carries measurement uncertainty, and a rate built from two results carries both. IEEE C57.104-2019 includes quality verification and the limitations of gas analysis. A 2023 study of uncertainty in that method highlights the concern near the detection limit, the smallest amount the method can reliably detect.
They also note that the 2015 edition of IEC 60599, the IEC interpretation guide, suggested assuming about 15% uncertainty for results more than ten times the detection limit, and about 30% below that, when nothing better is known. Differences between laboratories can be larger: the 2007 CIGRE paper notes that round-robin tests, in which several laboratories analyse the same oil, may show deviations of up to 44%.
Compare results from the same laboratory and method wherever you can, and ask for the uncertainty of each gas at the level you are reading. Give a gas that has just crossed the reporting limit particular care; a new number does not by itself establish a new fault.
The IEEE guide itself does not rely on a single two-point rate. As the Strathclyde paper describes it, the guide looks separately at the change since the previous sample and at a rate fitted through several results spread over 4 to 24 months. The transformer component maker Reinhausen gives the same 4 to 24 month window for that fitted rate.
What could another sample tell you in three weeks?
A small difference may be hard to distinguish from measurement variation. But an uncertainty interval is not a universal detection threshold, and crossing it is not proof of a fault.
Here is a bounded calculation, separate from the IEC percentage quoted above. Assume two results near 50 ppm, each with an expanded uncertainty of 7.5 ppm and coverage factor k = 2. Each standard uncertainty is then 3.75 ppm.
If the results are independent, the standard uncertainty of their difference is √(3.75² + 3.75²) = 5.3 ppm. Applying the same k = 2 gives an expanded uncertainty of about 10.6 ppm on the difference. NIST's guidance on combining standard uncertainties and expanded uncertainty explains the calculation. This example holds the absolute uncertainties fixed for the arithmetic.
THE SAME THREE WEEKS
How much change could build up?
Three assumed daily rates. One 21-day window. One scale.
2 ppm a day
42 ppmabout 5 days to accumulate 10.6 ppm at this rate
0.5 ppm a day
10.5 ppmabout 3 weeks to accumulate 10.6 ppm at this rate
0.1 ppm a day
2.1 ppmabout 15 weeks to accumulate 10.6 ppm at this rate
10.6 ppm is the assumed uncertainty on the difference between two results.
The bars compare increases over the same three weeks; the note below each bar gives the time that rate takes to accumulate 10.6 ppm. These times are not minimum sampling intervals, detection guarantees or deadlines. No resolved change over a short interval does not prove that a fast rise is absent.
Reinhausen's worked example shows the same trade-off. With 10% uncertainty and a true rise of 1 ppm a day, two samples 10 days apart can even look consistent with a falling gas, while samples 100 days apart give a more robust trend. A longer baseline is slower to react, though. Ask the laboratory and transformer engineer to choose the comparison rule using the actual uncertainties, correlations between results and the risk of a missed or false change. The site's required response still comes first.
For the data hall in the opening, that points to a plan the team can agree with its transformer engineer:
- Confirm, if the engineer calls for it. Use the same valve, laboratory and method, with the record below. Agree reporting time before collection. A prompt repeat checks whether the change repeats; it does not replace urgent action or guarantee a resolved trend.
- Compare either side of the load change. Where load dependence needs checking, Reclamation asks whether the gas rate rises and falls with load, with a sample each time load changes. Under the engineer's plan, a confirmation shortly before switch-on can serve as the before result; the after sample follows once the new load has settled.
- Continue the series. The engineer sets intervals from gas levels, measured rate and the guide in use, shortening them if the rate rises. Reclamation's table ranges from annual to daily sampling as levels and rates climb, but derives from the twice-superseded 1991 IEEE guide. Use that principle, not its old numerical schedule.
Each sample in this plan is timed to answer one question before the decision that depends on it. None of the timings is a universal rule.
Name the liquid and the interpretation guide
Interpretation guidance depends on what is in the tank. IEC 60599:2022 covers equipment filled with mineral oil and insulated with paper or pressboard. Its abstract calls for caution with other insulation systems and engineering judgement for any resulting action. In India, the same edition is adopted as IS 10593:2023.
Write the liquid and its product name on the sample form, then agree the interpretation guide and edition with the engineer. IEEE C57.104-2019 concerns mineral oil transformers. For natural or synthetic esters, the separate IEEE C57.155 guide needs a status check: its 2014 edition is inactive while a revision is prepared. Do not carry mineral oil rules across by habit. Edition details and revision links are in the references.
The record that travels with the syringe
For the load change in three weeks, a request that says only "repeat DGA" leaves too much open. Send the earlier report, the operating history and the decision date with the sample request. Agree collection and reporting times, rather than finding out after dispatch that the result will arrive too late.
Send this record with the syringe
Identify the sample
- Transformer: ID, rating, liquid type and product name.
- Collection: valve used and flushing procedure; syringe ID; bubbles expelled during filling and any bubbles formed afterwards left in and noted.
Capture the conditions
- Operation: continuous energised time, load and top-oil temperature.
- Changes: overloads, through-faults, nearby lightning, cooling problems, oil top-up or treatment since the previous sample.
- Custody: sampling and dispatch dates and times, laboratory receipt time, authorised sampler and permit reference.
Set up the comparison
- History: previous report numbers, laboratory and method.
- Decision: what the result must inform and when it is needed.
That gives the laboratory enough context to discuss measurement uncertainty and comparability, and the engineer a record against which to judge the rate. The next report may strengthen a trend or leave it unresolved. Either is more useful when the team knows which question the sample was collected to answer.
Planning the confirmation sample?
Tell us the transformer, the liquid, the report you have and the date the decision is needed. We will confirm the tests, the sampling container, the shipping route and the quoted timing before collection, and state where each test will be performed.
Common questions
Can we compare this result with last year's if a different laboratory tested it?
You can set them side by side, but read the difference with care. The cited round-robin work found substantial differences between laboratories. That is not the same quantity as a laboratory's reported uncertainty. If you switch, discuss paired samples for one round with the laboratories and your engineer so any step between methods can be assessed.
Should the new racks wait for the confirmation result?
The transformer's owner makes that call with its engineer under the site's operating rules. Do not wait for a repeat sample where an existing protection, manufacturer or site requirement calls for action. Agree sampling, shipping and reporting times against the decision date; neither this article nor a planned sample approves switch-on.
Our transformer is a dry type. Does any of this apply?
No. Dissolved gas analysis needs an insulating liquid to sample. Dry-type transformers are assessed by other means, under their manufacturer's guidance.
References
Sources reviewed on 19 October 2026. For IEC, IEEE and ASTM documents we read the publishers' public abstracts, scopes and status pages, not the full paid standards. Where we describe how IEEE C57.104-2019 treats changes and rates, we rely on the published summaries cited below. Reclamation's manual dates from 2000 and its numerical tables come from a superseded IEEE edition, so we cite it for sampling practice and arithmetic only. Citing a method does not establish VeriFluid's accreditation or availability for a particular sample.
- ASTM D3612-02(2026): Analysis of gases dissolved in electrical insulating oil by gas chromatography
ASTM International. Public scope and significance (sections 1.1, 1.2 and 5.1): gases covered, and the use of gas type, amount, rate and change over time.
- FIST 3-30: Transformer Maintenance
US Bureau of Reclamation, last updated October 2000. Sections 4.4.2 to 4.4.4 and Table 5 notes (pages 35 to 40): comparison with earlier analyses, rate per day of service, sampling interval logic, load dependence, confirmation sampling. Section 4.6.7 (pages 66 to 70): valves, syringes, bubbles, sunlight, negative pressure.
- E. Bräsel, U. Sasum, J. Aragon-Patil and S. Tenbohlen: Improved monitoring of dissolved transformer gases on the basis of a natural internal standard
CIGRE colloquium, Bruges, 2007; authors from Gatron and the University of Stuttgart; paper hosted by the University of Stuttgart. Pages 2 to 4 and conclusions: round-robin deviations, effects of air bubbles, sunlight, storage at 60 °C and stray gassing at 90 °C on syringe samples, and the recommendation to store samples at room temperature in the dark.
- IEC 60567:2023: Oil-filled electrical equipment, sampling of free gases and analysis of free and dissolved gases in mineral oils and other insulating liquids, guidance
IEC, edition 5.0, 8 December 2023. Public abstract: oil sampling from equipment moved to IEC 60475:2022, clause 4.2; extraction and gas chromatography.
- IEC 60475:2022: Method of sampling insulating liquids
IEC, edition 3.0, 25 May 2022. Public abstract: equipment covered and liquids covered, including esters and silicones.
- IEC 60599:2022: Mineral oil-filled electrical equipment in service, guidance on the interpretation of dissolved and free gases analysis
IEC, edition 4.0, 25 May 2022. Public abstract and status: scope, caution for other insulation systems, engineering judgement; edition 5.0 listed as under development with publication forecast for 26 February 2027 (checked 19 October 2026).
- IS 10593:2023 / IEC 60599:2022
Bureau of Indian Standards record: identical under dual numbering.
- IEEE C57.104-2019: Guide for the interpretation of gases generated in mineral oil-immersed transformers and project PC57.104
IEEE Standards Association. Abstract and status pages: active standard; revision project authorised 22 May 2024.
- M. Hosseini and B. G. Stewart: Propagating uncertainty using IEEE Std C57.104-2019 dissolved gas analysis methodology for transformers
23rd International Symposium on High Voltage Engineering, 2023; accepted manuscript, University of Strathclyde. Section 1: how the IEEE guide uses levels, changes and rates; uncertainty guidance in IEC 60599 (2015 edition).
- A. Alber: Calculation of DGA trends, offline vs. online
Maschinenfabrik Reinhausen. Description of the IEEE C57.104 rate calculation for laboratory results (fitted line, 4 to 24 month window) and the uncertainty of short baselines.
- IEEE C57.155-2014: Guide for interpretation of gases generated in natural ester and synthetic ester-immersed transformers
IEEE Standards Association status page: inactive-reserved since 27 March 2025; revision project PC57.155 active.
- VeriFluid: Transformer insulating-oil analysis and method library
Programme scope and representative methods; listing a reference is not an accreditation or capability claim.
- NIST TN 1297, section 5: Combined standard uncertainty and section 6: Expanded uncertainty
NIST, 1994 guidance, public pages reviewed 20 October 2026. Standard uncertainty, covariance and coverage factors support the expressly hypothetical calculation, not a transformer sampling deadline.
This article gives general guidance on sampling and planning. It does not set limits, diagnose faults, declare any transformer safe or give operating instructions. The gas values, rates and uncertainty in the figure and table are assumed for explanation and are not typical or permitted values. Site electrical safety rules, the transformer manufacturer's instructions and the owner's chosen interpretation guide take priority.